Plumbing and electrics first-fix
Coordinating pipe and conduit routes before walls are closed

Hawalli
First-fix plumbing in Mubarak Al-Abdullah begins with mapping vertical and horizontal pipe routes before the structure rises. We locate main stacks near kitchens and bathrooms and run supply and waste with full pressure testing before masonry and render.
Mubarak Al-Abdullah residential projects have deep plots with front and rear gardens, giving flexibility in stack positions. Bathroom and kitchen waste runs straight down without sharp bends then turns gently horizontal before reaching the floor chamber. Hot water lines need robust insulation because the voids under floor can be cold in winter, so we use polyethylene foam at least 25 millimetres thick.
Mubarak Al-Abdullah sits in Hawalli governorate, a spacious residential suburb where first-fix plumbing needs careful planning for long distances between stacks and floor chambers.
All vertical stacks are run continuously for a full day before closing because hairline joint cracks cause hidden seepage under new walls.
Coordinating pipe and conduit routes before walls are closed
Hot, cold and waste lines run to every sanitary point
Supply for sink, appliances and gas line inside the structure
Full pipe runs per unit including meter point positions
Drain lines laid to correct falls with proper vent stacks
Ground and roof tank connections integrated during structural stage
How we work

Tell us what is happening and where, and the right equipment is loaded before we arrive.

We film the line from inside and know the kind of blockage and its exact place. No guessing.

High pressure water, a machine or a drain snake, whichever the line actually needs.

The camera runs a second pass and you see the line clear with your own eyes before we leave.
Same method, same equipment. Only the size of the job changes.




Why us
Amana means trust. Someone else's home is not ours to be careless in.
Do not take our word for it. Look at the line yourself.
Breaking is the last resort, never the first step.
A blocked line does not wait for the morning.
Six governorates, 139 areas.
For buildings and complexes, servicing before the problem starts.
Restaurants, offices and complexes, not only homes.
Common questions
Need someone now? The emergency line is open any hour.
+965 9668 4964
Yes, but we need the structural engineer's approval because the main stack might run close to a load-bearing column. We redraw the horizontal branches and supply lines and retest everything before building starts.
Polyethylene foam 25 to 30 millimetres thick keeps 85 percent of initial temperature over a 20-metre run. Thicker wrap makes fitting difficult in tight voids without meaningful heat gain.