Crack welding
direct thermal weld along each fracture line in the tank wall

Ahmadi
Tank welding at Zour addresses cracks and damaged joints in massive cooling and water treatment tanks for the power station. We locate the crack by injecting colored water then drain the tank and remove any overlapping pipes from the work area. We scour the crack with stiff wire, fill it with deep-setting resin compound and test the seal under full operating pressure before completion.
Zour power station relies on massive fibreglass tanks mounted on tall steel frames above ground. These tanks face cyclic heating from cooling and chemical treatment cycles which weaken the resin and cause cracks around inlet and outlet pipes. We test every bolted joint with a torque wrench because over-tightening causes cracks around holes. Re-welding small cracks during scheduled maintenance stops water loss before it reaches critical levels.
Zour lies in Ahmadi governorate, where power generation depends on a steady supply of treated water without interruption.
We keep the tank in full standby for four hours after welding because the resin sets slowly at the high operating temperature.
direct thermal weld along each fracture line in the tank wall
re-welding inlet and outlet fittings where the flange joint has failed
resin-and-mat layer over the damaged zone before the final weld seal
internal camera after welding reveals any weak point before refilling
replacing the tank lid when the leak source is the cover seal
written record of weld locations and camera inspection result
How we work

Tell us what is happening and where, and the right equipment is loaded before we arrive.

We film the line from inside and know the kind of blockage and its exact place. No guessing.

High pressure water, a machine or a drain snake, whichever the line actually needs.

The camera runs a second pass and you see the line clear with your own eyes before we leave.
Same method, same equipment. Only the size of the job changes.




Why us
Amana means trust. Someone else's home is not ours to be careless in.
Do not take our word for it. Look at the line yourself.
Breaking is the last resort, never the first step.
A blocked line does not wait for the morning.
Six governorates, 139 areas.
For buildings and complexes, servicing before the problem starts.
Restaurants, offices and complexes, not only homes.
Common questions
Need someone now? The emergency line is open any hour.
+965 9668 4964
More slowly than heat alone but the compound causes the inner surface to dry out. We choose the weld resin to match the type of chemical treatment used in the tank.
No, all inlet and outlet pipes must be disconnected first and the tank fully drained. Disconnection and draining takes at least two hours before welding can begin.